You May be Able to Record Successive Mechanic's Liens

Print PDF
The determination of the expiration of the lien recording period can be complicated and depends on a number of factors. The completion of the project and whether or not a notice of completion was recorded affects the lien recording period. Another scenario occurs where the project was never completed but construction ceased. A notice of cessation may or may not have been recorded. Still another consideration is your status in relation to the project. Your lien recording time will depend on whether you were an original contractor, subcontractor, or material supplier.

A California case addressed the issue of recording of successive liens. In the case, a lien claimant had recorded a mechanic’s lien but did not file a lawsuit to foreclose the lien within the required 90 day period following the recording of the lien. After a dispute arose over the presence of the old lien, the lien claimant recorded a release of lien that stated, in substance, that the old lien was released and discharged. There was nothing in the recorded release that stated that the obligation on which the lien had been based was ever satisfied.The party opposing the lien claimant argued that the recording of the release of the old lien acted to release all lien rights that the claimant had in the property and that the lien claimant could not later record another lien. The appellate court disagreed with that contention.

The court held that the claimants lien rights could only be released where the release stated that the claim had been fully satisfied. The lien rights could be lost, however, where the claimant’s right to a lien, upon which the claim of lien was based, was extinguished.

Whenever an old lien is released so that a new lien can be recorded, special care should be taken to assure that the wording of the lien release does not cause the loss of any still effective lien rights.
You are here:   HomeNewsColumns & ArticlesYou May be Able to Record Successive Mechanic's Liens